Pouring Concrete into Haunches and Completing Plumbing Rough-In for Pool
Thursday, November 20th, 2008Bill Brown’s team and Michael Benison’s team continued to work in parallel on site in complete harmony.
Thanksgiving is approaching rapidly and, as they say, ‘pressure makes diamonds.’
Pouring Concrete into Haunches
There was a small pumper truck for the haunches. Everything was set up nicely and the pouring was completed.
Completing Plumbing Rough-In for Pool
The plumbing for the swimming pool continued to progress nicely.
Michael advised me to move the inspection well to the north side of the pool (from the west side). This allowed us to take advantage of the existing excavation.
Next step is for the City of Monte Sereno to inspect the plumbing rough-in and the rebar in the swimming pool.