Drilling the Final 5 Piers to Support Our Walls

Of the 25 concrete piers that are required, 5 of those piers will support steel beams that will, in return, support the existing walls of the house.

All of the piers have been completed, except these final five piers. Until now, the rebar cages have been 30 ft long, now the rebar cages are 38 ft long.

More rain is forecasted so today is (another) big day.

The driller picks up the first 38 ft rebar cage.

The driller picks up the first 38 ft rebar cage.

The driller moves from the back of the site to the front, with the rebar cage.

Moving to the front of the site with the rebar cage.

Driller moves to the front of the site with the rebar cage.

And positions the cage to be lowered into the hole.

Positioning the rebar cage over the hole.

Positioning the rebar cage over the hole.

Guiding the rebar cage into the hole (note the plastic spacers to keep the rebar cage at least 3 inches from the side of the hole).

Guiding the rebar cage into the hole.

Guiding the rebar cage into the hole.

Putting on more plastic spacers.

Pausing to put more plastic spacers on the rebar cage.

Pausing to put more plastic spacers on the rebar cage.

The first extended rebar cage is now in position.

First rebar cage is now in position.

First rebar cage is now in position.

With the cage in position, we need the concrete pumper truck and a mixer with concrete.

Concrete pumper and mixer in place, ready to pump concrete.

Concrete pumper and mixer in place, ready to pump concrete.

Here is the entire team, pumping concrete into the hole.

Mixer, pumper truck and drill.

Mixer, pumper truck and drill.

The tremie is at the bottom of the hole and we’re pumping concrete (note the operator with the wireless console).

Pumping concrete into the hole.

Pumping concrete into the hole.

Of course, both the soils engineer and structural engineer were on site to observe and verify that the process was being completed by the contractors as per the specifications that were approved by the City of Monte Sereno.

Engineers on site inspecting the concrete piers.

Engineers on site inspecting the concrete piers.

Thien Dong (Duquette Engineering) and Jerry Freeman (JF Consulting).

Thien Doan (Duquette Engineering) and Jerry Freeman (JF Consulting).

Here is a great photo of the casing being removed from the hole with the tremie in the background, waiting to be lowered back into the hole and complete pumping the concrete.

Removing casing from hole with tremie in background.

Removing casing from hole with tremie in background.

We’re almost done. Here you can see the east side being completed.

Casing coming out of hole with tremie in background.

Casing coming out of hole with tremie in background.

And we’re almost done.

Bryan managing a big smile as we're nearing completion on a beautiful, blue-sky California day.

Bryan managing a big smile as we

Bryan managing a big smile as were nearing completion on a beautiful, blue-sky California day.

Bryan managing a big smile as we're nearing completion of the drilling on this beautiful, blue-sky California day.