Pool Walls and Backfilling is Complete

Yesterday, while I was attending Ernst & Young’s 2008 Financial Reporting Development workshop in Mountain View (hey, I need those CPE credits!), Michael and his team completed backfilling the pool and compacting the soil.

Today, I was on site for our weekly construction progress meeting at 9:00 am and was impressed with the work completed yesterday.

After the meeting, I went to the City of Monte Sereno and learned that my permit was not ready to be issued. Daylight is burning …

Charlie Touchatt, the excavator and hauling sub-contractor, visited the site in the afternoon and we went to a potential site that needs soil in the Santa Cruz Mountains. Charlie, who is a native of San Mateo and has been involved with the development of the peninsula over the past 50 years, shared some interesting stories with me as we drove back to 17509.

Spa

SpaGood Compaction on Backfill

Deep End of Pool Looks Good

Deep End of Pool Looks GoodSteps Into Pool

Elevations were Taken from the Monument

Elevations were Taken from the Monument

Steps Out of Deep End

Steps Out of Deep End

Compaction Behind Free-Standing Wall

Compaction Behind Free-Standing Wall

Ready for the Pool Cover Now!

Ready for the Pool Cover Now!