Placing the Geotextile Fabric over the Underslab Drains

Monday, January 12th, 2009

After the weekend, everyone was rested and keen to use the great weather to complete the infrastructure to prepare for the shotcrete walls and the working slab.

Drain from stairwell to sump, which will penetrate the waterproofing.

Drain from stairwell to sump, which will penetrate the waterproofing.

Pete Janovich directing Bill Brown's team.

Pete Janovich of Bill Brown Construction directing the team.

Preparing excavation for sewage ejector in south-east corner.

Preparing excavation for plumbing in south-east corner.

Pete reviewing site work.

Pete reviewing site work.

Geotextile fabric in pllace, ready for 3/4 inch crushed rock.

Geotextile fabric in pllace, ready for 3/4 inch crushed rock.