Placing High Load 40 Styrofoam
With the 3/4 inch crushed rock groomed for the plumbing drains and the corresponding compaction completed, the crew placed the Dow High Load 40 rigid styrofoam in place. After taping, they will prepare the Pre-Prufe waterproofing membrane over the styrofoam sheets.
Bryan and his father drilled a hole and put the 10 ft pole on the temporary site office so it can support the Davis weather station. This was a two-person job that had to be completed before John returns to winter in Edmonton, Canada.
Bryan’s father, John, struggles with a smile, knowing he returns to Edmonton, Canada tomorrow where it truly is winter!