Storms Are Coming
Wednesday, February 4th, 2009After such fabulous sunny winter weather, the rains are coming. The team worked hard all day, knowing that the storms are approaching.
With more intense work in the basement, a solid set of steps into the basement was built, coming off the steps leading down from the driveway.
The actual rough-in for the plumbing started today, with the first pipes being fitted to the sewage ejector.
Rebar Arrives for Mat Slab
The delivery truck from Whitecap arrived with a load of rebar. They brought a forklift, which unloaded the rebar near the steps to the basement. Yes, it was carried down by hand.
Setting Up Tarps
In the later afternoon, the tarps were set up to protect the site from the storms, which will arrive late tonight and through the next few days.