Working in the Rain

Friday, February 6th, 2009

The rains arrived today in Los Gatos.

With the tarps over most of the site, it was relatively dry and work continued as the insulation was fixed to the west wall.  As well, the Grace Preprufe 160R was placed on the forms on the north and south walls.

Insulation on the west wall and Grace Preprufe 160R on the forms on the south wall.

Insulation on the west wall and Grace Preprufe 160R on the forms on the south wall.