Coordination While Placing Rebar

Wednesday, February 11th, 2009

It was the second day for placing the rebar on the working slab.  There is much coordination that needs to be done as we are planning to pour the structural slab late next week.

For example, any conduit going in the slab needs to be in place quickly.  For our structure, we’re going to run two 2 inch conduits from the Mechanical East room to the Mechanical West room.  This will allow us to have two 200 amp electric panels in the house, connected with conduit that can hold the required amount of wire.

Protective caps on the rebar placed yesterday.

Protective caps on the rebar placed yesterday.

  (more…)