Back to the Job Site

After a fabulous week in Argentina, it is back to the job site.

Athough work has progressed, there was plenty of rain in the past week.  The key activities under way are to complete all the components so the 14 inch structural slab can be poured.  The structural slab will be on top of the 3 inch protection slab that was poured on February 2.

In order to pour the structural slab, the plumbing rough-in must be completed as well as the electrical conduit that is in the concrete.  The sewage waste must flow by gravity to the sewage ejector, so this is a significant milestone.  Having electrical conduit in the concrete simplifies the wiring and reduces the need for chases through the ceiling and walls in the lower level.

Importantly, any steel columns supporting steel beams must be set in the concrete, so these components must be placed accurately (or the steel columns won’t line up with the steel beams).

Prior to pouring the structural slab, the reinforcing steel (rebar), steel plates, plumbing rough-in and electrical conduit must be inspected by the City of Monte Sereno.

OK, we’re getting on top of this project …

In terms of decisions, we’re now reaching the point where finishes are being established.  For the concrete floors, we need to decide on how we want our concrete floors finished.  This is important as it is hard to change later (go figure).  Looking ahead, windows and doors need to be ordered and finalized, too.

We came across some very interesting and durable polished concrete.  This could be worth further investigation (and knowing how much it will cost).  You can see three different colors in this photo.

Stained and polished concrete.

Stained and polished concrete.

 An important issue that needs to be addressed relates to the design of the drains from the stair well and window well to the 36 inch vertical culvert at the south-east corner of the house.  The City of Monte Sereno requested additional detail on this design.  This must be completed prior to pouring the structural slab.  Another item on the list …

Status at the Job Site

The following photos show the status of what is in place at the job site as of Monday afternoon on Feb 23.

Plumbing and electric conduit in place.

Plumbing and electric conduit in place.

Plumbing rough-in going to Guest Suite (blue tinge in photos is from the tarps).

Plumbing rough-in going to Guest Suite (blue tinge in photos is from the tarps).

Plumbing rough-in for services on west side of lower level.

Plumbing rough-in for services on west side of lower level.

Plumbing rough-in for floor drains in East Air Handler room.

Plumbing rough-in for floor drains in East Air Handler room.

Two layers of reinforcing steel on south side of lower level.

Two layers of reinforcing steel on south side of lower level.

Two 2 inch electrical conduits between the two layers of reinforcing steel that will take power from the main panel in the East Mechanical room to the sub-panel in the West Mechanical room.

Two 2 inch electrical conduits between the two layers of reinforcing steel that will take power from the main panel in the East Mechanical room to the sub-panel in the West Mechanical room.