Working in the Rain

The rains arrived today in Los Gatos.

With the tarps over most of the site, it was relatively dry and work continued as the insulation was fixed to the west wall.  As well, the Grace Preprufe 160R was placed on the forms on the north and south walls.

Insulation on the west wall and Grace Preprufe 160R on the forms on the south wall.

Insulation on the west wall and Grace Preprufe 160R on the forms on the south wall.

 

Insulation on west wall and Grace Preprufe 160R on forms on north wall.

Insulation on west wall and Grace Preprufe 160R on forms on north wall.

Overview of site from temporary deck over swimming pool.

Overview of site from temporary deck over swimming pool.

The forms around the sewage ejector excavation were removed.  Next steps are to put in the rebar for the pouring of the 14 inch structural slab (on top of the 3 inch working slab). 

Forms removed from sewage ejector, ready for rebar and structural slab.

Forms removed from sewage ejector, ready for rebar and structural slab.