Managing the Job Site
It was a beautiful blue-sky, California day today. A dirigible appeared in the sunshine, circling over Los Gatos and the Santa Cruz Mountains.
Discussion with Matt Jung
Matt Jung from 88HVAC met Bryan at the job site to discuss the geothermal and radiant heating requirements and timing. The last time Matt was at the site was in November 2008 so a lot had changed since them.
We need to establish all ducting requirements prior to completing the concrete walls.
Sweeping Up
Kate and Nik arrived in the late afternoon to help prepare for the week ahead.
Pockets and Hold Downs
Just before leaving, we photographed the pockets and hold downs around the site today. Bill Brown scheduled the shotcrete for Wednesday, April 8 so everything has to be in place prior to the inspection on Monday afternoon, April 6.