Testing Soil Compaction
Tuesday, June 2nd, 2009Our soil compaction was to be completed to at least 90%
It was.
Soil Compaction
Our soils report stated, ‘The drainage material and the clayey soil cap should be placed in layers about 6 inches thick and moderately compacted by hand-operated equipment to eliminate voids and to minimize post-construction settlement.’
We engaged HP Inspections to test our soil compaction throughout the backfill process, which they did.
Today, the final testing was completed.
We’re good.