Our Posts are In!

With sprinkles in the weather forecast for Monday and rain on Tuesday, we needed to complete welding the final nine posts in place.  We had welded five of the fourteen posts on Thursday.

Welding the Posts

Tony Gutierrez and ‘Little Pete’ arrived just after 8:00 am this morning at our project site.  It was foggy and a bit cool.

Bryan had the site prepared and the remaining posts laid out.  We were able to start quickly and soon completed the welding on post 33, at the top of the stairs.  This was a complex post as it needed base plates put in and grinding so we could align the bottom of the post correctly.

After post 33, we put post 28 in place, which is on the corner.  This one was a bit tougher and went ok.  Then, we struggled with post 27, an intermediate post.  Finally, it lined up on the third attempt.  We all wanted it perfect.

Back to the top of the staris and we put in post 32, which lined up nicely with post 28.  However, the next intermediate post, post 29, required cutting into the hollow core so we could weld it on all sides.  Posts 29 and 30 were a snap.

Posts in protective wrapping from Paramount Iron Railing Systems

Posts in protective wrapping from Paramount Modular Cable Railing Systems

Little Pete welding a shim in place for post 28.

Little Pete welding a shim in place for post 28.

Tony holding post 28 in place while Little Pete welds it.

Tony Gutierrez holding post 28 in place while Little Pete welds it.

Tony holds post 27 as Little Pete tacks it in place. We got this one right on the third try.

Tony holds post 27 as Little Pete tacks it in place. We got this one right on the third try.

 Reed and Cole Drop Off a Router

We need to put some temporary railings on the posts so Reed Kingston came by with one of his boys, Cole, and dropped off a router.  They did a quick tour of the site and even tested the stairs.

Reed pointing out some key elements in the plans for his son, Cole.

Reed pointing out some key elements in the plans for his son, Cole.

Cole and Reed posing behind the plan table.

Cole and Reed posing behind the plan table.

We’re Done

Then, we moved to the front of the house, to weld posts 16 and 19 into place.  These are the first posts our visitors will see when they enter the house.   Post 16 was perfect.  Post 19 was a bit tough as the cap plate was rotated by 90 degrees.  Tony assessed the situation and explained how we could fix it easily.  Fifteen minutes later, it was in place.

We finished by tacking covers over five openings in the steel where concrete could possible flow when we continue pouring.

Then, we packed up and were done.  Bryan closed and locked the gate just before 2:30 pm.

Our posts are in!

Looking up from the bottom of the atrium. It was a beautiful, blue-sky California day.

Looking up from the bottom of the atrium. It was a beautiful, blue-sky California day.

Our posts are in and looking great!

Our posts are in and looking great!

Posts 33 (left) and 32 (right), showing the bracings, etc. that will buried in concrete shortly.

Posts 33 (left) and 32 (right), showing the bracings, etc. that will buried in concrete shortly.

Completed posts. Very nice.

Completed posts. Very nice.

Posts 16 (left) and 19 (right), which are the first two seen when coming in the front door. Note the clean face of the posts (no holes).

Posts 16 (left) and 19 (right), which are the first two seen when coming in the front door. Note the clean face of the posts (no holes).