Preparing for the Rains

The forecast is for 100% probability of rain tomorrow.  It was time to ensure the site office is watertight and the site is ready for rain.

Bryan had a good design session with Scott this morning at Hotel Los Gatos.  Scott and Sue are were there last night and are staying in San Francisco tonight before returning to Toronto tomorrow morning.

Design Discussion with Scott

Scott reviewed the plans and, after seeing the space yesterday, outlined the lighting plan for each of the rooms.  Scott and Bryan reviewed a number of alternatives for the atrium, gable roofs, and exterior.  During the discussion, Scott recommended that we consider including some art niches in the wall by the Bridge Hall.  We will definitely be following up on this one.

For the atrium and feature concrete wall, Scott is going to put some light fixture samples together so we can ‘test’ how the lights will wash the concrete wall.  These samples are not for the fixtures but, rather, so we can see what type of lighting we would prefer.  This will help Scott in recommending which fixtures to use.

Scott, Sue and Bryan then went to the project site so they could consider the design alternatives relative to the space.  After 45 minutes, Scott and Sue left for San Francisco.

Scott, on Canadian Thanksgiving, reflecting on the bridge.

Scott, on Canadian Thanksgiving, reflecting on the bridge.

 

Bryan and Scott discussing lighting alternatives and how to show our feature concrete wall.

Bryan and Scott discussing lighting alternatives and how to show our feature concrete wall.

Scott and Bryan discussing design alternatives.

Scott and Bryan discussing design alternatives.

 

Scott explaining how to the test lights will work.

Scott explaining how to the test lights will work.

Buttoning Up the Temporary Site Office

Given the weather forecast, Bryan spent several hours buttoning up the project site.  Importantly, he put a new tarp over the temporary site office roof to help reduce the probability of leaks tomorrow.

Our Davis weather station looked good today.  We’ll see exactly how much rain and wind our site receives tomorrow.

The site is looking secure with our first winter rain storm arriving shortly.

The site is looking secure with our first winter rain storm arriving shortly.

Bryan put primer on the exposed steel, where the bridges and posts were welding on Saturday.

Bryan put primer on the exposed steel, where the bridges and posts were welded on Saturday.

Ends of Bridge Hall, primed and ready.

Ends of Bridge Hall, primed and ready.

New blue tarp on the roof of our temporary site office.

New blue tarp on the roof of our temporary site office.

Our Davis weather station, ready to log the rainfall and winds tomorrow.

Our Davis weather station, ready to log the rainfall and winds tomorrow.