Starting to Form the Finished Floor

With the PEX in place, Bill Brown’s team was back on the critical path.

They had to complete placing the reinforcing steel (rebar) over the PEX and form the perimeter where the concrete ends and the hardwood floor starts.

That said, the garage is complete and we’re pouring concrete tomorrow morning!

The first few pieces of rebar are over the PEX (and the 6-6-10-10 wire mesh).

The first few pieces of rebar are over the PEX (and the 6-6-10-10 wire mesh).

The PEX is in place and pressurized to 100 psi.

The PEX is in place and pressurized to 100 psi.

Looking toward the North wall, you can see the layout of the PEX and how the first pieces of rebar are being placed.

Looking toward the North wall, you can see the layout of the PEX and how the first pieces of rebar are being placed.

The garage is being completed as it still needs to be poured.

The garage is completed and it will be poured tomorrow.