Archive for the ‘Electrical’ Category

Continuing to Work with PG&E

Wednesday, October 5th, 2011

Nothing is easy.  We thought we were there with PG&E and, surprise, we’re not there yet.

We did start to move the control system for our sliding glass doors at the back of the house into the permanent location in the East Storage room.

Yes, it poured rain, starting at ~3:00 am for a couple hours.  Our site handled the rain just fine.

Moving the Door Control System into East Storage Room

When the control system for the three sliding glass doors at the back of the house was set up, we were not ready to mount the control system in its permanent location, which is in the East Storage room.  Now, it is time to do so.

The control system, made by Doors in Motion, requires a dedicated 15 amp circuit and has four wires going from the DC electric motor to the control system, including the switch.  The four wires, which have multiple conductors, are for the power (the transformer to DC and backup battery are housed in the control system), the door switch (open, close, stop, lock, reset), the motion detector, and the encoder unit itself.

We decided to run the wires in a dedicated conduit containing only low-voltage wires.  The conduit is the flexible, orange corregated one-inch conduit by Carlon.  We’ve been obtaining our low voltage products from ADI in Santa Clara.  Hank Malloy and Jordan have been extremely helpful in sourcing the correct products for us.

The conduit included the four wires for the door and the CAT5e wires for the lighting control system (C-bus).  The lighting control system includes a pink CAT5e and a yellow CAT5e.  The pink wire is for the main system and the yellow wire is for a backup (redundant).  All other data CAT6, with a spline, will be blue.

When connecting the wires to the door control system, we found a problem.  Jason Cruz, who installed the door control system, helped Bryan to isolate the problem.  They didn’t solve the problem yet and should complete it tomorrow.

Installing Our Permanent Electric Meter

Although the two-person crew from PG&E installed our permanent electric meter on Monday, October 3, they didn’t have the correct meter for a 400 amp service.  Knowing that the meter would be changed again to a bi-directional meter for our solar photovoltaic generation system, they put in a 200 amp meter.  However, PG&E’s process and internal systems still show our temporary service in place as the correct meter had not been installed.

Thus, PG&E dispatched a meter technician to our job site to install the permanent meter for our 400 amp service.  The meter technician, AJ, smiled as he installed the correct meter saying, ‘I’ll be back in a couple days to install the bi-directional meter that will measure your generation and your electric vehicle consumption.’

We’re just following the process …

Motor for our sliding glass pocket doors at the back of the house. We need to have the wires to connect the control system to the motor in a dedicated conduit.

 

The path for the flexible conduit will go through the Dining Room, into the soffit and through to the East Storage room.

 

The one-inch orange conduit will join the two-inch 'smurf' tubes in the soffit going to the East Mechanical room.

 

 

The door control system will be located permanently in the wall to the left of the three lighting control system panels.

 

We're taking the opportunity to install the 1-1/2 inch polyisocyanate insulation against the concrete throughout the lower level (basement). We removed this insulation from the roof and stored it so we could use it again. This insulation will be covered with spray foam, encapsulating it. Note there is two inches of rigid foam insulation outside the concrete wall.

 

The meter technician from PG&E, AJ, installs the correct Smart Meter for our 400 amp service. This meter replaced the 200 amp meter that was installed on Monday. The next meter that will be installed is the bi-directional smart meter for our solar photovoltaic generation and time-of-use electric vehicle (E-9) rate service.

 

 

Installing Our Permanent Electric Meter

Monday, October 3rd, 2011

With our permanent meter in place, we’re a step closer to our rebate.  Every day we seem to get closer …

It rained today and is forecasted to rain through Wednesday.  We are prioritizing our activities to keep our materials dry … bone dry.

Installing Our Permanent Electric Meter

Before we can have an electric meter for our solar generation, we need to have a permanent electric meter in place.  To have a permanent electric meter, we required a ‘meter release’ from the City of Monte Sereno.  The meter release was issued by the City of Monte Sereno on September 29, which was our rebate filing deadline.

Bryan called PG&E several times this morning and learned that our permanent meter was scheduled to be installed on Wednesday, October 5.  Knowing this was delay, Bryan started to call our various contacts at PG&E.  When speaking with the scheduler, Barbara Aker, Bryan explained that if a crew was available at the last minute then we would be ready to have our meter installed.

To our delight, Barbara called and said that a crew came available and they could install our permanent meter today.

Way cool!

Portable Charger for a Nissan LEAF

While getting some parts for Al at Electrical Distributors in San Jose, Bryan noticed a Nissan LEAF in the parking lot.  Bryan spoke with the owner of the LEAF, who explained that he was assembling a portable charging station that could plug into various types of 240 volt circuits.  Further, he explained, the benefit would be to use 240 volt circuits that are available in RV/trailer parks.

Installing charging stations in RV/trailer parks could be done quickly and easily, which would help deploy the infrastructure for electric vehicles across the U.S.

An interesting idea …

The two-person truck arrived at our job site at ~ 11:30 am this morning.

 

The service entrance panel had to be secured and then sealed before the meter could go in.

 

Our permanent meter is in! This meter will be replaced with a 'net meter' that will measure the electricity that we generate and send into the grid.

 

Charging station that can be used in RV/trailer parks for charging a Nissan LEAF.

 

Hosting Scott and Sue’s Visit to California

Friday, September 30th, 2011

Scott Andersen and Susannah Therrien flew into San Francisco yesterday and will return to Toronto on Sunday.  Scott, from Toronto, has been involved in the design of our remodel and construction since inception.

Al, Dan and Nep continued on the rainscreen while Bryan ensured we met the remaining obligations under our indemnification agreement with the City of Monte Sereno.

Finishing the Week

Bryan had made arrangements to have yellow and black warning signs made for the two live electric panels.  This morning, he picked up those signs and put one on the service entrance panel outside the house.  The other sign was for the 200 amp electric panel in the East Mechanical room.

We completed insulating the ceiling in the Wine Cellar and Wine Dining today.  The soffit needs to be insulated and that will be completed on Monday.  Next steps with the Wine Cellar will be to use closed cell spray foam and fill the cavity and create a moisture barrier.  The Wine Cellar will be at a much higher humidity than the house and exterior, so we need to ensure that moisture remains in the Wine Cellar.  After with moisture barrier is in place, we will be able to install the radiant cooling panels in the ceiling.

Al, Dan and Nep completed the siding on the East side of the house and started on the rainscreen on the South side of the house.  They will complete the rainscreen on Monday, before the first real rains of the season are forecasted to start on Wednesday.

Spending the Afternoon and Evening with Scott and Sue

Scott and Sue arrived at the job site just after 12:00 noon today.  Bryan took them on a quick tour, during which Scott opened the sliding glass door at the back of the house.  Both Scott and Sue were impressed, with Sue noting that their sliding glass door in Panama could be improved with the controls that we are using in California.

As a visitor, Scott had to go for a test drive in a Tesla Roadster 2.5 Sport, which Bryan enjoyed too.  Yes, Scott had the ‘Tesla smile’ after his test drive.

Since Jo-Anne was finishing the quarter in Boston and returning to California tomorrow morning, Scott, Sue and Bryan went to Enoteca La Storia.  Bryan showed them the empty bottle of 1961 Louis M. Martini Cabernet Sauvignon, which we opened at the 50/50 party on April 16, 2011 at Enoteca La Storia. 

After Enoteca, Scott took Sue and Bryan to Steamer’s Grillhouse in Los Gatos, where Scott arranged for a table instantly.  It was a excellent ending to a great day.

Tomorrow, after a lighting design session on the job site, we’re hosting Scott’s 51st birthday dinner at Nick’s on Main

Scott, after pushing the button, watches as our three-panel 24 ft sliding glass door opens.New yellow and black warning sign on the service entry electric panel on the East side of the house.

 

New yellow and black warning sign on the service entry electric panel on the East side of the house.

Warning sign, in English and Spanish (thank you for the translation Darryl!).New yellow and black warning sign on 200 amp panel door in East Mechanical room.

 

 

Completed insulation in the ceiling of the Wine Cellar.

 

Completed insulation in the ceiling of the Wine Dining. Note the wine racks in the background.

 

Rainscreen assembly and radiant barrier on the South wall of the house.

 

Primed furring strips over the radiant barrier create a 3/4-inch air gap for air to flow and to allow the radiant barrier to reflect heat.

 

Scott, with the 'Tesla smile', after returning the Roadster 2.5 Sport to the dealership on Santa Row.

 

Scott enjoyed the Roadster!

 

Sue, Bryan and Scott in Enoteca La Storia, with the empty bottle of 1961 Cabernet from the 50/50 party held there on April 16, 2011.

 

Bryan explained to Scott and Sue, 'It was a great bottle of wine but ... it was a bit young.'

 

Everyone enjoyed dinner at Steamer's Grillhouse.

 

We enjoyed a great bottle of 2005 Altagracia.

 

Signing Up for Acterra’s High Energy Homes Project

Friday, September 23rd, 2011

When Bryan was in the City of Monte Sereno’s offices yesterday, he saw a flyer for Acterra’s High Energy Homes Project.  Curious, he took a copy of the flyer and followed up today.

Also, our ferrules arrived this afternoon so now all we need is the pink CAT5 and then we can wire our C-Bus network that will connect all our switches and sensors.

Ferrules and Pink CAT5

We’re at the point where it is time to run the CAT5 around the house to every switch and sensor location, and then back to the six control panels in the house.  Schneider Electric’s C-Bus system requires either a daisy chain topology, star cable topology, or combination daisy chain and star cable topology.

To connect the CAT5 in either daisy chain or star cable topologies, we need to physically connect the CAT5 cables together.  In addition, although there are eight individuals conductors (wires) in a CAT5 cable, two pairs of the wires must be connected together.

For the C-Bus system, the orange and blue wires are connected with a 'bootlace crimp' as are the orange-white and blue-white wires. The green and green-white, and brown and brown-white are not connected.

While trying to find a ‘bootlace crimp’, Bryan learned that the the correct term for the connector is a ‘ferrule’.  Ferrules are used in Europe and other countries to connect stranded and other wires to devices.

At the same time, Bryan learned that, under the Australian electrical code, all C-Bus wiring must use pink CAT5.  This is to identify the wire uniquely so it is not confused with data wiring.

Bryan ordered two boxes of pink CAT5 from ADI, and strips of 500 1.0 mm ferrules (red), 1.5 mm ferrules (black) and 2.5 mm ferrules (blue) from Rob at Ferrules Direct.  Each switch in the C-Bus system come with two 1.0 mm ferrules.

The ferrules and crimping tool arrived today.

Signing Up for Acterra’s High Energy Homes Project

Using his handfree speakerphone, Bryan called the contact name in Acterra’s High Energy Homes Project flyer, Davena Gentry, and learned about the project.  Essentially, Monte Sereno is the fifth highest energy-using towns (based on a per household energy use) out of the 225 cities served by Pacific Gas & Electric.

Acterra is a tax-exempt not-for-profit organization whose mission is to ‘bring people together to create solutions for a healthy planet.’  Apterra has served Silicon Valley for over 40 years.  Here is a great video clip about Acterra.

Apterra applied for a grant from the California Energy Commission to fund on-line studies for residents of Atherton, Los Altos Hills, Monte Sereno, Portola Valley and Woodside.  These are five of the seven highest energy-using cities that PG&E serves.

Monte Sereno is the fifth highest energy-consuming city that Pacific Gas & Electric serves.

For Monte Sereno, if the average annual electric use per residence is 13,000 kWh and the cost per kWh is $0.40 then the average annual electric bill is approximately $5,200 per year.  Or, more than $425 per month.  This usage is more than double the average electric use of 6,000 kWh per year.

The graph below shows the energy consumption per residence of each of the 225 cities that PG&E serves.

Monte Sereno's average electric usage per residence is ~13,000 per kWh.

Here is a link to the presentation made by Acterra to Portola Valley Town Council on December 9, 2009:

http://www.portolavalley.net/modules/showdocument.aspx?documentid=2834

We signed up for the remote assessment regarding our rental property at 17740 Vista Avenue so we will see if there are any no-cost measures that we can take to reduce our resource consumption at our rental house.

 

Buttoning Up the Ladder in the Vertical Culvert

Friday, September 16th, 2011

We can stroke this one off the list – the ladder inside the vertical culvert is done.  Bryan was at the bottom of the vertical culvert on December 8, 2010.  It feels good to get this element of the project completed.  Finally.

As well, we finished off the solar installation and now we need to get connected to the grid.

Excellent progress …

The ladder and safety post are now mounted securely inside the vertical culvert.

View from the bottom of the vertical culvert (17 feet to the surface).

We put a wooden plywood deck inside the vertical culvert so we could add the electrical and other components safely and quickly.

The cast aluminum ring and manhole cover fit nicely over the vertical culvert.

Panels inside the East Mechanical room ...

 

Panel open with spacers over deadfront, with labeling. Ready for inspection ...

 

Our solar permit, which needs to be signed off and closed.

Although we are connected to the grid, this permit should be closed.

 

Inspecting Our Photovoltaic Solar Panel Installation

Tuesday, September 13th, 2011

The City of Monte Sereno reviewed our photovoltaic solar panel installation and signed off on all the components that Real Goods Solar are responsible for.  The one remaining component is a cover for the 200 amp electrical panel in the East Mechanical room.

Although the cover is required, there is no current flowing through our electrical system as we are not connected to ‘the grid’.

We were honored to have Bob Sobota and Eufermiro Cariaga from Schneider Electric, and Jim Laberty of Lighting Systems tour our project site today.  Bryan met Bob Sobota when Bryan attended the C-Bus training course in Palm Desert in March 2011; Bryan had hosted Jim’s visits to our project site previously, and it was Eric Westphal and Jim that recommended that we engage Randall Whitehead Lighting Solutions to design the lighting throughout the house.  Eufermiro and Bryan met for the first time today.

Bob works in the lighting controls division and Eufermiro is in the Juno Lighting Group.  Jim Laberty is the local distributor for both C-Bus lighting controls and Juno lighting.

Changing Our System to 100% Micro-Inverters

Solar photovoltaic panel installations are new and evolving.  One of the technology elements that is continuing to evolve is the inverter.  Usually, an entire array of panels (or string of arrays of panels) are connected to a single inverter.  The inverter takes the DC and converts it to AC.

For our installation, we changed the design from a mix of one string inverter (for 32 panels) and 16 micro-inverters, to 48 micro-inverters.  Changing to all micro-inverters reduces the conductors (wiring), increases the efficiency of the electricity generation, and increases the safety of the overall system.

One of the challenges with micro-inverters is that not many people understand how these systems work.  Liam Ryan, from Real Goods Solar, explained the details to Bryan.

Before Operating, Micro-Inverters Require a Connection to the Grid

Generally, when solar photovoltaic panels are exposed to sunlight they produce electricity.  The panels create direct current (DC) electricity and that flows to the inverter.  In the case of a micro-inverter, the transmission of DC is only a couple of feet as the micro-inverter is mounted to the panel.  The micro-inverter then creates alternating current (AC) which is connected to the building’s electrical system.

Enphase micro-inverters are ‘UL-listed’ as they have been certified (tested and approved) by Underwriters Laboratories.  Products certified by Underwriters Laboratories are identied with a UL Mark.  According to Underwriters Laboratories’ web site:

The UL Mark on a product means that UL has tested and evaluated representative samples of that product and determined that they meet UL requirements. Under a variety of programs products are periodically checked by UL at the manufacturing facility to make sure they continue to meet UL requirements. The UL Marks may be only used on or in connection with products certified by UL and under the terms of written agreement with UL. In addition to these marks, UL also provides access to the marks required in a number of other key world markets.

Liam explained that the Enphase micro-inverters in our system cannot convert the DC current to AC unless the micro-inverter has recognized the 60 Hz wave form has been stable for five minutes.  The 60 Hz wave form is present in the electrical grid throughout the U.S. and Canada.  Thus, the micro-inverter cannot create AC current unless our system is connected to the grid.

In addition, Liam explained that the micro-inverters will stop creating AC current immediately upon losing recognition of the 60 Hz wave form.  The software in the Enphase micro-inverters is what recognizes the 60 Hz wave forms and then controls the output.

Underwriters Laboratories has certified the Enphase micro-inverters that we are using.

Consequently, although we have our entire solar photovoltaic system built, installed and inspected, we cannot create electricity until we are connected to the grid.  There is no electricity present in our system.

Roseanne Prevost-Morgan and Matt Knobbe of Real Goods Solar dropped by our site to take a quick look at the installation. Bryan, of course, took their picture on the Upper Flat roof.

 

Green Home Building

Mid Century Style
Powered By Ringsurf