Archive for the ‘Engineering’ Category

Staying on Track

Thursday, March 25th, 2010

Our project is complex and we’re doing our best to stay on track. 

However, our non-maleable building materials (i.e., concrete, glass and steel) make it difficult to correct mistakes or make other changes and, consequently, we’re taking more time and money than we had planned for this project.  That said, a LEED-H Platinum project, by definition, requires more thoughtful planning, material sourcing and handling, and documentation than otherwise.  Especially in an earthquake prone location with increasing seismic conditions.

So, comparing our budget, timeline and other elements to traditional projects, which are generally energy- and resource-intensive, is not appropriate.  But, no surprise, that comparison, and evaluation of our project management, is done by others every day. 

If we were using traditional building materials with traditional construction methods (i.e., stick framing, wooden floor joists and roof rafters, baseboards and door trim) then we should be on a much faster timeline and a lower budget.

We just need to get over it.

Assembling the Lower-Level Flat Roof

Around the entire perimeter of the house is the ‘lower-level flat roof’.  The ceiling height of this roof is identical to the existing house at 96 inches (8 ft).  The only exception to this is the roof at the back of the house, which sits above the lower-flat roof, which we call the ‘mid-level flat roof’.  Yesterday, the entire perimeter roof was completed as the mid-level flat roof connecting the Dining Room and Kate’s Bedroom was assembled.

Way cool.

Steel Flush Beam in SIP Roof

There is only one steel beam in our SIP roof and it is a flush beam that is hidden inside a SIP.  This is a critical beam that supports the upper-level flat roof over the Atrium and allows us to have only one post in the Kitchen area.  And, of course, have an extremely strong structure that meets the new code requirements for seismic conditions.

This steel flush beam sits on top of a lower-level roof SIP over the Garage and goes over the steel post in the Kitchen and is connected to a 7.00 x 11.25 inch Paralam beam that sits on the 8×12 Douglas Fir drop beam.  This steel beam will carry lateral forces into the concrete wall in the Garage so it must be connected robustly to that concrete wall.

The fabrication of the steel beam must include:

  • 5/8 inch Nelson studs to attach 2×6 nailers on the top and bottom;
  • a hole in the top and bottom flange to connect the beam to a 5/8-inch anchor bolt that is embedded in the concrete wall;
  • a Simpson GLT welded to the north end of the steel beam to connect it to the 7.00 x 11.25 Paralam flush beam;
  • two sets of 5/16 inch stiffeners welded in the locations where there are vertical loads (i.e., over the concrete wall and over the steel column);
  • four sets of plates welded to the flanges of the steel beam to connect to the 4×6 and 6×6 posts that support the upper-level flat roof; and
  • four bolts connecting the steel beam to the HSS 4×4 steel column in the Kitchen.

The steel beam must be the correct length and each of the components noted above must be in the correct locations.  Yeah, there is a lot going on with this steel beam.

Hosting Thien Doan’s Site Visit

Duquette Engineering designed the concrete foundation for the structure and Thien Doan did most of the work under Steve Duquette’s supervision.  Thien was at our project site numerous times observing the drilling of the holes for our concrete piers as well as the placement of the reinforcing steel (rebar) in the concrete slabs. 

When Steve Duquette attended our integrated project planning meeting on March 9, 2010, he said that he would like Thien to come by at this interim point in the project and take some pictures.

Thien came to the site today and walked the property with Bryan.  Thien was most interested in the SIPs and how the SIP wall and roof assembly was designed to transfer the shear forces to the concrete foundation walls.  Thien appeared impressed with the design and the construction, noting that there would probably be limited cracking of the sheet rock in the house during an 8.8 earthquake.

Reviewing the Shop Drawings for the Steel Beam with Larson Steel

Bryan drove to Larson Steel’s fabrication shop in Gilroy and met with William Zapeda to go over the measurements they took on Friday, March 19, prior to fabrication of the W8×18 steel beam.  They went over each of the measurements, noting one key area where Bryan needs to confirm with the lead framer from Earth Bound Homes, Francisco Espinoz.

William and Bryan went in the yard and reviewed the actual W8×18 steel beam and measured it.  The beam was a beautiful blue color, which is exactly what we would like the exposed steel beams and two steel columns to look like.

Finding Curb Damage in Los Gatos

The City of Monte Sereno requested that we have three 1-1/2 inch pipes carrying our excess water from our underground cistern to the curb on Winchester Boulevard, where it would then flow into the storm drain.  The engineers from the Town of Los Gatos did not like this design and requested that we connect our underground cistern with an 8-inch pipe connecting directly to the back of the storm drain.

They cited potential damage and maintenance issues as the reasons for requesting this change.  Today, Bryan saw a location where the 1-1/2 inch drain went though a concrete curb and had subsequent cracking and damage. 

Now, we can appreciate the request for a direct connection.

ArchiCAD rendering showing the W8x18 steel beam and the lower-level SIP roof.

ArchiCAD rendering showing the W8x18 steel beam and the lower-level SIP roof.

ArchiCAD rendering showing steel beam and posts supporting the upper-level flat roof structure.

ArchiCAD rendering showing steel beam and posts supporting the upper-level flat roof structure.

Mid-level flat roof at the back of the house.  This is where the three sliding glass panel doors will be located, which will go into a pocket behind the exposed concrete feature wall at the left of this photo (the Dining Room wall).

Mid-level flat roof at the back of the house. This is where the three sliding glass panel doors will be located, which will go into a pocket behind the exposed concrete feature wall at the left of this photo (the Dining Room wall).

View from the middle of swimming pool to the front door, showing the mid-level SIP roof that was assembled yesterday.

View from the middle of swimming pool to the front door, showing the mid-level SIP roof that was assembled yesterday.

Thien Doan, from Duquette Engineering, on the lower-flat roof over the Garage.

Thien Doan, from Duquette Engineering, on the lower-flat roof over the Garage.

View of Master Study and Master Bedroom showing completed 2x4 wall under 6x10 beam in Foyer and pony walls ready to receive the posts and ridge beams to support the SIP gable roof.

View of Master Study and Master Bedroom showing completed 2x4 wall under 6x10 beam in Foyer and pony walls ready to receive the posts and ridge beams to support the SIP gable roof.

Thien taking photos of the SIP roof structure.

Thien taking photos of the SIP roof structure.

Simpson Strong Tie HTT22 connecting the 6x6 post to the hollow core concrete panels.  Solid.

Simpson Strong Tie HTT22 connecting the 6x6 post to the hollow core concrete panels. Solid.

LPT4s in the Master Bedroom, reinforcing the SIP walls to the 6x10 flush beams in the SIP roof structure.

LPT4s in the Master Bedroom, reinforcing the SIP walls to the 6x10 flush beams in the SIP roof structure.

Exposed feature concrete wall at the back of the house, showing the space for the pocket that will hold the three sliding glass panels.  Note that we will be adding a drop beam under the mid-level flat roof.

Exposed feature concrete wall at the back of the house, showing the space for the pocket that will hold the three sliding glass panels. Note that we will be adding a drop beam under the mid-level flat roof.

Measuring the profile of the W8x18 steel beam in Larson Steel's yard in Gilroy.

Measuring the profile of the W8x18 steel beam in Larson Steel's yard in Gilroy

The W8x18 beam is 5-1/4 inches wide.

The W8x18 beam is 5-1/4 inches wide.

We like the blue color of the steel and are considering having all of the exposed structural steel in the house finished in gun-metal steel blue.

We like the blue color of the steel and are considering having all of the exposed structural steel in the house finished in gun-metal steel blue.

Concrete curb in Los Gatos, showing damage caused by the 1-1/2 inch pipe going through the curb.

Concrete curb in Los Gatos, showing damage caused by the 1-1/2 inch pipe going through the curb.

At the end of each day, Jo-Anne does her best to drop by and review our progress.  With the longer days and the time change, it is easier for her to do so.  And, it is always good to see her smiling!

At the end of each day, Jo-Anne does her best to drop by and review our progress. With the longer days and the time change, it is easier for her to do so. And, it is always good to see her smiling!

Building SIP Ponywalls, Hosting Visitors, and Presenting Our Project

Wednesday, March 17th, 2010

We have a sense of urgency to complete our project.  Our feelings are heightened when it is raining. But today we throroughly enjoyed a beautiful, blue-sky California day.  Spectacular!

Our tasks included building our SIP pony walls and hosting Jerry’s Kauffman’s class from San Jose City College.  In between, we were absolutely delighted, and honored, to host Dawn and Steve’s first visit to our project site.  We’re counting on their return visit in the next six months (before we complete our project).

Building Our SIP Pony Walls

Our roof is a bit complicated although we like to think it is simple.  There are three types of connections for our gable roofs to connect to our flat roofs, and several other connections for each of the lower- and mid-level flat roof to post connections and multiple post to top level flat roof connections.  All of these connections come together over the corner of the Garage/Atrium, where our concrete wall is that goes all the way to the foundation (18 ft).

Putting the SIPs into this area was difficult as there were numerous anchor bolts and we added five 1-inch threaded steel rods, each embedded 12 inches into the concrete.  Adding to the complexity was the rigid conduit to carry the DC current from our 48 solar photovoltaic panels to the two inverters, located in the East Mechanical room.

Oh, the other component in this area is an 8×18 steel beam that connects the roof structure over the Living Room to the concrete wall in the Garage/Atrium.  This steel beam needs to be fabricated and is located inside the mid-level SIP roof.  The trick when working with steel is to have accurate measurements as it isn’t very maleable once fabricated.  Unless you have a cutting torch and arc welding equipment on site.

Hosting Dawn and Steve’s First Site Visit

Jo-Anne arrived at the project site with Dawn and Steve.  We took them on a full tour of the house, going through every room.  Both Dawn and Steve are from the Boston area so our Eichler and ‘California Modern’ design was very different than the residential architecture that they see on the East coast. 

They were impressed with the ‘green’ aspects of our project and wanted information on the payback of our solar photovoltaic panels.  Apparently, Massachusetts doesn’t have as many bright, sunny days as we enjoy in California.

Dawn mentioned that her husband, Dave, would be most interested, and impressed, with the insulated header in the West wall of the house.  Steve thought our temporary site office was over the top.

They promised to return and see our project again.

Presenting Our Project to San Jose City College Students

Jerry Kauffman, who we had met at the Kaneda Residence, was at our second Collaborative Informational Session last week and had arranged with Bryan to bring his students to tour our project.

The 20 students arrived promptly at 5:45 pm and toured the entire site.  Bryan gave an overview of our objectives and construction challenges and then took the students through each room, highlighting the innovative building materials and ‘green’ features.  The students had many questions, which Bryan did his best to answer concisely and accurately (he may have pontificated a few times).

The tour concluded on the SIP roof.  All 20 students climbed the ladder up to the roof and walked around the perimeter.

It was the perfect time at this point in our construction for the students to see how SIPs are assembled on site.  They could see the lower-flat roof in place and how the 2×6 plates are connected, with the pony walls going on top of the plates to support the SIP gable roof.  Moving around the roof, they saw the shear wall assemblies with the straps connecting the joints on the top of each beam.  Also, they saw the connections on top of each Hardy Frame.  Bryan distributed samples of the ‘blue screws’ that connect the SIPs so everyone could appreciate how the connections were made.

The presentation concluded at 7:30 pm and Bryan locked the gate just as it was starting to get dark.

Connection between the lower- and mid-level flat SIP roofs over the Garage/Atrium concrete wall, including the anchor bolts and LPT4s.

Connection between the lower- and mid-level flat SIP roofs over the Garage/Atrium concrete wall, including the anchor bolts and LPT4s.

Note the strapping at the right side that will connect the bottom of the nailer on the steel beam (to be fabricated) to the top of the SIP roof over the Garage, which is then connected to the concrete wall in the Garage/Atrium.  There is a lot going on in this location!

Note the strapping at the right side that will connect the bottom of the nailer on the steel beam (to be fabricated) to the top of the SIP roof over the Garage, which is then connected to the concrete wall in the Garage/Atrium. There is a lot going on in this location!

Carlos is caulking the bottom of the pony wall SIP where it will be placed over the 2x6 plate.  This pony wall will support the SIP gable roof over the Kitchen.

Carlos is caulking the bottom of the pony wall SIP where it will be placed over the 2x6 plate. This pony wall will support the SIP gable roof over the Kitchen.

We uncovered the SIPs and staged the pony wall SIPs on the roof.  The large SIPs stacked on the temporary pool cover are for the gable roofs.

We uncovered the SIPs and staged the pony wall SIPs on the roof. The large SIPs stacked on the temporary pool cover are for the gable roofs.

Dawn arrives at our project site!

Dawn arrives at our project site!

Immediately after arriving, Steve receives an important call.

Immediately after arriving, Steve receives an important call.

Dawn, Steve and Jo-Anne enjoyed the full tour in the late afternoon sunshine.  Amazingly, all of them stayed clean through the tour of our active construction site.

Dawn, Steve and Jo-Anne enjoyed the full tour in the late afternoon sunshine. Amazingly, all of them stayed clean through the tour of our active construction site.

As they were leaving, Dawn received a call (note her shoes for the tour).

As they were leaving, Dawn received a call (note her shoes for the tour).

Jerry Kauffman, right, as his class assembles to review our project.

Jerry Kauffman, right, as his class assembles to review our project.

After touring the lower level (basement) and ground floor, everyone climbed the ladder to the SIP roof.

After touring the lower level (basement) and ground floor, everyone climbed the ladder to the SIP roof.

The students made their way around the SIP roof, as they reviewed the connections and the SIP details.

The students made their way around the SIP roof, as they reviewed the connections and the SIP details.

Bryan's presentation concluded with final questions on the roof.

Bryan's presentation concluded with answering questions on the SIP roof.

The group had plenty of questions, which Bryan did his best to respond to concisely and accurately.

The group had plenty of questions, which Bryan did his best to respond to concisely and accurately.

Note the horizontal strapping that ties the blocking together in the SIP over the concrete wall between the Kitchen and Garage.  This will be covered by a 2x12 tomorrow.

Note the horizontal strapping that ties the blocking together in the SIP over the concrete wall between the Kitchen and Garage. This will be covered by a 2x12 tomorrow.

Bringing Our Reclaimed Beams Home

Friday, February 19th, 2010

We completed several tasks on our critical path to completing our SIP roof today.  An important task was to have all of the beams on site so they could be graded.  Having our beams is critical so the structural framing can be completed on the ground floor so we can move the SIPs onto the roof with the crane on Wednesday.

Picking Up Our Reclaimed Beams After Milling in Watsonville

Dave Merchant, from Out of the Woods, loaded the three beams that we milled to size on Tuesday at his site in Bonny Doon.  Dave met Bryan in Watsonville at Jackel Enterprises, where we loaded the remainder of the beams that were being milled.  From there, Bryan followed Dave up Highway #1 and over the hill to our project site.  There, our framing crew unloaded the beams by hand and staged them for grading.

Charlie Jourdain, from Redwood Inspection Service in Pleasant Hill, arrived on our site as planned and the beams were ready for him.  Charlie examined and graded each beam, then stamped the end of each beam.  He will be sending us a certificate stating the grade of each beam.  Note that Redwood Inspection Service is a division of California Redwood Association, of which Charlie is the President.

Loading our recently milled reclaimed Douglas Fir beams in Watsonville.  The beams on the truck were milled by Dave Merchant in Bonny Doon.

Loading our recently milled reclaimed Douglas Fir beams in Watsonville. The beams on the truck were milled by Dave Merchant in Bonny Doon.

Bryan followed Dave's truck back from Watsonville.  Dave is going up Winchester Boulevard with our reclaimed beams.

Bryan followed Dave's truck back from Watsonville. Dave is going up Winchester Boulevard with our reclaimed beams.

Dave backed the trailer into our site so it could be unloaded quickly and easily.

Dave backed the trailer into our site so it could be unloaded quickly and easily.

Charlie Jourdain, President of California Redwood Association, came to our job site and graded our reclaimed beams.  Charlie is measuring the grain of the wood as the grain runs diagonally in this beam.

Charlie Jourdain, President of California Redwood Association, came to our job site and graded our reclaimed beams. Charlie is measuring the grain of the wood as the grain runs diagonally in this beam.

Charlie measured and graded all of our beams on site, which were just delivered a few hours ago.

Charlie measured and graded all of our beams on site, which were just delivered a few hours ago.

Making Insulated Headers

On the West side of our house we have two bathrooms.  The beams that support the SIP roof at the front and back of the house extend through the building.  However, we have two bathrooms on the West side and, even with exhaust fans, these bathrooms will have a high moisture content.

To provide greater protection from condensation, our durability plan requires insulated headers to keep keep the surfaces of the exposed beams warmer and prevent condensation from occuring. 

From two of the reclaimed Douglas Fir beams, we had Jackel Enterprises cut two 1-3/4 inch wide planks.  Using these planks, we sandwiched 2 inches of rigid R-10 insulation.  Thus, we end up with an insulated header that is 5-1/2 inches wide and over 19 ft long.  This insulated header will be over the windows in the two bathrooms.

Similarly, we require a small insulated header on the East side of the house, above the exterior Kitchen door.

Francisco makes the insulated headers by sandwiching 2 inches of rigid insulation between two planks, cut from our reclaimed Douglas Fir beams.

Francisco makes the insulated headers by sandwiching 2 inches of rigid insulation between two planks, cut from our reclaimed Douglas Fir beams.

Completed insulated header.  The two pieces of reclaimed Douglas Fir are held together by a number of 4-1/2 inch galvanized SDS screws, countersunk into the planks.

Completed insulated header. The two pieces of reclaimed Douglas Fir are held together by a number of 4-1/2 inch galvanized Simpson Strong Tie SDS screws, countersunk into the planks.

Moving the Temporary Steel Beams

The temporary steel beams supporting the existing East and West walls of our house were moved clear of the structure today.  Several inches of the concrete haunches were removed so the existing walls are now free and clear, and are entirely supported by the house once again.

We’re ready to remove the temporary steel beams from the site on Wednesday, February 24.

Reducing Construction Waste

Renovation and construction projects can generate a tremendous amount of waste that goes to landfill sites.  According to the LEED for Homes Reference Guide, ‘Construction and demolition wastes constitute about 40% of the total solid waste stream in the United States.’  For our project, we are targeting to create as little construction waste as possible.  When our Green Rater, Darrel Kelly, came to our project site on Tuesday, February 16, he was surprised, and delighted, to see how little waste we were generating as we were using three 35 gallon garbage bins to hold our framing debris.

Earth Bound Homes delivered a trailer to our job site today that will be used for all the framing debris.  All the framing waste on our job site was dumped into the trailer as it will be taken for recycling.  We will obtain tags on the debris removed with the trailer.

This is the trailer from Earth Bound Homes, which contains all of our framing debris to date.  Note that a number of the pieces in trailer are reclaimed wood, which would otherwise be landfill.  This debris will be taken for recycling, not landfill.  Reduce, reuse and recycle (redirect).

This is the trailer from Earth Bound Homes, which contains all of our framing debris to date. Note that a number of the pieces in trailer are reclaimed wood, which would otherwise be landfill. This debris will be taken for recycling, not landfill. Reduce, reuse and recycle (redirect).

Overview and Inspection of Progress this Week

Given the days are longer now, Jo-Anne was able to drop by the job site at the end of the day today to inspect our progress. 

Our first major shear wall is in place in Kate’s bedroom (formerly the Master Bedroom).  Having the shear wall in place prior to Jo-Anne’s inspection showed significant progress. 

In line with that shear wall is another shear wall adjacent to the Atrium.  Scott Andersen, who did the conceptual design of the remodel, specified during his most recent job site progress review that we include recessed art niches in the wall behind the glass bridge to the Master Suite.  Three recessed art niches were framed in today and the plywood will be nailed in place next week.

Jo-Anne walked the property and was smiling as she was pleased with our progress this week.

Completed SIP walls on either side of our doorway at the front of the house.

Completed SIP walls on either side of our doorway at the front of the house.

Same view of the foyer, taken on September 29, 2008 when the roof was being deconstructed.

Same view of the foyer, taken on September 29, 2008 when the roof was being deconstructed. Note the diagonal brace on the temporary site fence through the door - it is the same diagonal brace in the photo above. Way cool.

Three art niches that are framed in the shear wall behind the glass bridge facing the Atrium.

Three art niches that are framed in the shear wall behind the glass bridge facing the Atrium.

Example of recessed art niches (not in a contemporary style house).

Example of recessed art niches (not in a contemporary style house).

Example of recessed art niches.

Example of recessed art niches on a large exposed wall.

Plywood 2x6 shear wall between the Living Room and Kate's Bedroom.

Plywood 2x6 shear wall between the Living Room and Kate's Bedroom.

Jo-Anne, standing in Kate's Bedroom, smiles as she walks the property inspecting our progress this week.

Jo-Anne, standing in Kate's Bedroom, smiles as she walks the property inspecting our progress this week.

Our flag is flying and our Insulspan sign is posted.  The site is buttoned up, ready for the rain that is forecasted through the weekend.

Our flag is flying and our Insulspan sign is posted. The site is buttoned up, ready for the rain that is forecasted through the weekend.

Green Home Building

Mid Century Style
Powered By Ringsurf