A number of project elements (tasks) are going to come together in the next week so we can start assembling our SIPs.
We now have an integrated and feasible short-term plan that will see our house rising out of the ground decisively by the end of March. The next week should be interesting to see unfold.
Overview
The major tasks in our short-term plan include the following:
- Order and receive remaining FSC lumber to complete the structural framing
- Detach the temporary steel beams from the existing East and West walls and move the temporary steel beams so they are clear of the structure
- Deliver milled reclaimed beams to our project site
- Grade the reclaimed beams
- Ensure the East and West walls are straight and plumb, and complete the shear walls
- Order the FSC lumber for the SIP roof sections
- Complete the single SIP wall and structural framing to support the SIP roof sections
- Receive the final four structural beams to support the SIP roof sections
- Remove the temporary steel beams and load them on a truck
- Move and stage the first stack of SIPs onto the structural framing to complete the lower flat roof
- Unload the FSC-certified lumber for the SIP roof sections
These tasks will result in having all the materials available over the next week to construct our SIP wall and SIP roof sections.
Order and Receive FSC Lumber to Complete the Structural Framing
Given the limited space available on our site, we have been ordering our FSC-certified lumber small orders so it can be stored easily and protected from the rain. Each order has had less than 10% estimated waste factor and the orders are following our detailed framing plans. We have a detailed cut list for each order to minimize the work on site. There is one final small order to be delivered that will provide sufficient lumber (2×6 plates and studs, and 4×8 posts) to complete the structural framing on the ground floor.
Bryan worked with Francisco, leading the on site work with Earth Bound Homes, today to confirm and place the order. It should be delivered between 7:30 and 10:30 am tomorrow morning.
Detach the Temporary Steel Beams
The existing East and West walls on the ground floor have been supported and held in place since the beginning of our project by two 60 ft long temporary steel beams. Now that the team from Earth Bound Homes have attached the existing walls to the concrete foundation walls, the walls need to be plumbed and trued. To do so requires detaching the temporary steel beams and moving the beams a few inches away from the structure on the concrete haunches.
Pete Janovich, from Bill Brown Construction, reviewed our requirements yesterday and confirmed today that he will be on site with two others tomorrow to complete this work. This task is on our critical path.
Deliver Milled Reclaimed Beams to Our Project Site
Bryan has been working with Out of the Woods and Jackel Enterprises to mill our reclaimed Douglas Fir beams to meet our specifications. Dave Merchant will be loading the beams that he milled yesterday and going to Watsonville to pick up the beams that Steve Jackel has milled. Then, Dave will bring the full load over the hill to Monte Sereno and unload them at our job site.
Steve will confirm everything is ready at his end so Dave and Bryan will meet there at noon tomorrow.
Grade the Reclaimed Beams
With the milled reclaimed beams at our project site, Charlie Jourdain, from Redwood Inspection Service in Pleasant Hill, will be in San Jose on another matter on Friday, February 19 so he will come to our project site and review and grade the reclaimed Douglas Fir beams.
The beams have to be available on the ground so Charlie can see all the sides of the beams. After the beams are graded, they will be installed as part of our structural framing to support the SIP roof panels.
Order the FSC Lumber for the SIP Roof Sections
The SIP roof sections have extremely detailed wood requirements. The shop drawings for each panel show the individual lumber connections that hold the panels together. Bryan will go through the shop drawings one final time this weekend, considering the remaining lumber we have on site, and place our order lumber on Monday.
This order of FSC-certified lumber will be delivered on Wednesday morning, February 24.
Complete the SIP Wall and Structural Framing
After plumbing the existing East and West walls, the framing team from Earth Bound Homes will complete the SIP wall at the front of the house and the structural framing on the West side of the house. They will use the FSC lumber that will be delivered tomorrow morning to do so.
After ensuring all the structural framing is plumb, they will use the FSC-certified plywood to complete the interior and exterior shear walls. The shear walls will increase the structural strength of the interior and exterior walls so they can support the SIP roof sections.
Receive the Final Four Structural Beams to Support the SIP Roof Sections
Earlier today, Bryan confirmed the order and delivery time for the final four structural beams that we require. These beams will be milled in Oregon from ’standing dead’ trees that are harvested in Idaho. While not FSC-certified, these timbers will be accompanied by a letter stating their origin and how they were harvested.
These are large beams, including one 8×12 beam that is almost 40 ft long. Bryan spoke with Lowell Tucker and scheduled West Coast Cranes to be on site to unload and place these beams. And complete several other tasks for the crane.
Remove the Temporary Steel Beams and Load Them on a Truck
When the crane is on site, we will be able to remove the two 60 ft long, 6,000 lb temporary steel beams from the East and West sides of the house. Pete Janovich will have a low-bed truck at the site that will take the beams away.
Move and Stage the First Stack of SIPs on the Structural Framing
With the site now ‘clear’, we will use the crane to stage the first stack of SIPs from the temporary cover on the swimming pool to the lower flat roof. Given the structural framing and shear walls have been completed, we will be able to stage the SIP roof panels so the lower flat roof can be built over the West side of the house.
These are the SIPs in front of the window of our temporary site office. We’re looking forward to seeing daylight in the temporary site office!
After this section of the lower flat roof is completed, we will have a larger staging area for the rest of the SIP roof panels.
Unload the FSC-Certified Lumber for the SIP Roof Sections
The final task for the crane will be to unload the truck with our final order of FSC-certified lumber. This lumber order will be quite large and need to be moved from the trucks and placed on the ground floor at our job site.
That’s the Plan
Plan your work. Work your plan.
Let’s get going.

View from behind the house to the street. We used string lines to show where the drop beams will go between the two feature concrete walls. The 'cabinet wall' between the Kitchen and Dining Room must line up perfectly under this structural beam and supporting post.

View from behind Simpson Strong Tie GLBT to show placement of our 8x12 wooden beam. The 'cabinet wall' must line up under this beam perfectly. Note the 'vanishing point' perspective with the string lines.

View showing the placement of the East beam. This will be a 6x12 beam that will be 'broken' over the post in the cabinet wall between the Kitchen and Dining Room.

The framing on the West side of the house is very compact. This is the area that needs to be completed as it is where we will be staging the SIP roof panels.

Our neighbor, Ned Gault, dropped by the job site and reviewed our progress to date. Ned had been in Florida and was curious to see how much progress we had made while he was away. Ned was pleased and is looking forward to the completion of our constrruction activities (aren't we all?).