Archive for the ‘SIPs’ Category

‘Tyveking’ Our Roof

Wednesday, August 25th, 2010

OK, ‘Tyvek’ isn’t a verb.  But, then again, neither is ‘Google’.  But everyone ‘Googles’ people, materials, terms, etc.  We ‘Tyveked’ our roof today.

Dave Edwards’ two-person team from Earth Bound Homes worked all day putting building wrap (Tyvek) over the flat and gable roofs.  The Tyvek needs to be in place before Akeena Solar puts in the solar mounts and conduit on the flat roof.  The installation team from Akeena Solar will be on site on Friday morning (08/27/10).

During the day, Bryan made several trips to pick up materials so the team could continue working.  These materials included 5 ft wide Tyvek, 9 ft wide Tyvek, and Stinger staples.  We don’t want the crew working to pause for a moment because they don’t have materials.  As well, we don’t want to have more materials than are required to complete our project (controlling and limiting our construction waste).

Also, White Cap delivered our expanding foam and more Grace Viecore Plus so we can have a robust air and water seal between the flat and gable roofs.

Finalizing the Plans for Our Solar Photovoltaic Panels

Akeena made the final changes to the plans for our solar mounting system.  Sheet PV-1 shows the layout of the 6 arrays of 8 solar panels on the flat and gable roofs.  Sheet PV-2 shows the details of how the arrays will be attached to the roof. 

We worked with Akeena (Duk Lee in particular) to design the mounting system to optimize the production of electricity and to reduce the number of cables and penetrations of the thermal envelope. The benefit of designing the system in advance is that the system should generate the maximum amount of electricity possible while maintaining limiting tripping hazards to make maintenance (cleaning) of the solar panels fast, easy and safe.

Delivery from White Cap to our project site.  Gino Anttanasio is taking good care of us.

Delivery from White Cap to our project site. Our account manager, Gino Attanasio, is taking good care of us.

Looking through the Atrium, the gable roofs are covered with Tyvek building wrap.

Looking through the Atrium, the gable roofs are covered with Tyvek building wrap. Note how the evening sunshine is going into the kitchen through (what will be) the clerestory windows.

Looking South on the lower flat roof, admiring the Tyvek on the roofs.  Note the chase for the conduit to the solar panels in the sunshine against the pony wall under the clerestory windows.  Also, note the four insulated skylight curbs.

Looking South on the lower flat roof, admiring the Tyvek on the roofs. Note the chase for the conduit to the solar panels in the sunshine against the pony wall under the clerestory windows. Also, note the four insulated skylight curbs.

The upper flat roof is covered with Tyvek.  Note the mounts for the solar panels in the lower left part of the photo.  Also, of course, note the beautiful blue-sky California day.

The upper flat roof is covered with Tyvek. Note the mounts for the solar panels in the lower left part of the photo. Also, of course, note the beautiful blue-sky California day.

The lower flat roof on the West side is covered with Tyvek.  Note the insulated curbs for the skylights and the first clerestory window in the box at the top left of the photo.

The lower flat roof on the West side is covered with Tyvek. Note the insulated curbs for the skylights and the first clerestory window in the box at the top left of the photo.

 

It was satisfying to see the Tyvek on the gable roof at the front of the house.  People driving North on Winchester Boulevard will see some progress on our house.

It was satisfying to see the Tyvek on the gable roof at the front of the house. People driving North on Winchester Boulevard will see some progress on our house.

Verifying Our Insulation Performance and Value

Friday, August 20th, 2010

We are getting closer to putting the tapered insulation down on our flat roofs so we can put the membrane on and get water tight.  Before doing so, we verified that the SIP roof has no ‘voids’ in the insulation where the individual pieces come together. 

In anticipation of the next step, becoming weather tight, Bryan picked up the first of 72 boxes of windows so we could confirm the window preparation requirements.  Since we will be seeing Carole Murray tomorrow, it is important to show that we’re progressing and getting the windows out of her warehouse!  Also today, Bryan continued working with Izzy on ensuring the HDPE coming out of each concrete pier can be joined to create our ground loop.

At the end of the day, Gino Attanasio from White Cap dropped off two more 10-lb containers of expanding foam for us to use in tightening up our building envelope.

Picking Up Our First Window

We have 72 boxes of sliding glass doors and windows at Murray Window and Door.  We can’t install the sliding doors and windows until we are weather tight.  Well, we probably could install them but we are choosing not to.

In anticipation of the first clerestory window installation, we picked up one of the 16 windows.  This will allow us to identify exactly how the windows will ‘fit’ and how we will need to attach the windows.  While we have shop drawings, it is always good to have the actual item on hand to avoid potential problems.

After hoisting the window up and onto the roof, we were able to see exactly how the clerestory windows will fit.  This was important as we may have a conflict with the nail fins and edge trim in each of the four corners where the two clerestory windows come together.

Using Thermal Imaging to Verify Our Insulation Value

In our house, the SIP panels are connected on the roof with either wooden I beams or 6×12 splines.  In either case, there is a possibility of leaving ‘voids’ in the EPS foam at these locations.  If a void is left then the insulation value of the roof is compromised.  Voids will reduce the insulation value much more than thermal bridges, which is another problem that we want to avoid.

Today, we took the opportunity to engage Lorna Fear, with Visual Cue Thermal Imaging, to spend a couple hours going through our project to verify that we didn’t have any voids between our SIPs.  Bryan and Lorna worked together, with Bryan explaining how the SIP construction worked and Lorna reviewing the thermal images and identifying where potential problems could be.  Lorna is an expert at interpreting the thermal images and ’seeing’ where there are inconsistencies in the building envelope.

The thermal imaging identifies different surface temperatures and displays those differences with different colors.  Since heat goes from hot to cold, a surface temperature that is colder than surrounding surfaces may indicate that the energy is being drawn into the building, through a less-insulated condition than the surrounding area.  However, surfaces may also reflect thermal energy, thus showing very ‘hot’ surfaces that may hide other problems.

Given her experience, Lorna can identify where potential problems may occur with our insulation.  Bryan asked Lorna to identify all potential problems locations as we can deal with ‘false positives’ at this stage.  If we miss a problem, it could be there for the life of the building.

Removing Concrete for Our Ground Loop

Bryan spent the afternoon with Izzy chipping away at the top of 6 of the 12 concrete piers on the West side of the house.  Ken Martin, from Silicon Valley Mechanical, fine-tuned the design of the geothermal ground loop so there are two ground loops on the West side that include six concrete piers in each ground loop.

Connecting the individual loops in each pier requires two 90 degree fittings and a short length of HDPE.  Then, the piers need to be connected to each other in a daisy chain manner, with a supply and return for each pier.  For the physical connection, Matt Jung (88HVAC) identified that we need a one-inch space for the cold ring and then another 4 inches to weld the fittings on.  Thus, there must be at least five inches of clear space on the top of each concrete pier where the connections will be located.

All of the piers need to be checked for sufficient space and, where additional space is required, the concrete must be removed.  Removing concrete is noisy, difficult and time-consuming (just ask Bryan). 

Picking up the first of 72 boxes from Murray Window and Door.  Bryan was smiling as he picked up the first box, especially since we will be seeing Carole Murray on Saturday afternoon at Black Ridge Vineyards.

Picking up the first of 72 boxes from Murray Window and Door. Bryan was smiling as he picked up the first box, especially since we will be seeing Carole Murray on Saturday afternoon at Black Ridge Vineyards.

We have the window on the roof, and unpackaged it so we could see exactly how it fit and what the potential issues would be when installing it (and its 15 other clerestory windows).

We have the window on the roof, and unpackaged it so we could see exactly how it fit and what the potential issues would be when installing it (and the other 15 clerestory windows).

 

Lorna, using her Fluke infrared thermal imaging camera, reviewing the South side of the South Gable over the Master Suite.

Lorna, using her Fluke infrared thermal imaging camera, reviewing the South side of the South Gable over the Master Suite.

Lorna uses her Fluke infrared thermal iimaging camera to review the upper flat SIP roof for voids.

Lorna uses her Fluke infrared thermal imaging camera to review the upper flat SIP roof for voids.

This is the thermal image with the surrounding image around it.  You can see the surface temperatures with the scale on the right hand side.

This is the thermal image with the surrounding image around it. You can see the surface temperatures with the scale on the right hand side.

Lorna using her Fluke infrared thermal iimaging camera, identified potenital locations where voids may be on the upper flat roof that need to be investigated.

Lorna using her Fluke infrared thermal imaging camera, identified potential locations where voids may be on the upper flat roof that need to be investigated.

On this thermal image you can see where the warm and cool locations are.  This therma image shows that there may be voids in the SIPs that need to be filled with expanding foam.

On this thermal image you can see where the warm and cool locations are. This thermal image shows that there may be voids between the SIPs that need to be filled with expanding foam.

Izzy and Bryan spent several hours removing concrete from the top of the concrete piers so the ground loops can be connected by 88HVAC.  Matt Jung of 88HVAC will be coming by the job site tomorrow (Sunday) to verify if additonal concrete needs to be removed.

Izzy and Bryan spent several hours removing concrete from the top of the concrete piers so the ground loops can be connected by 88HVAC. Matt Jung of 88HVAC will be coming by the job site on Sunday to verify if additional concrete needs to be removed.

Summarizing Our Construction Progress for the Week

Saturday, July 31st, 2010

It was a beautiful, blue-sky California day.  The morning fog lifted around mid-morning, leaving a warm, but not too hot, day.

Perfect for documenting our progress at the job site this week.

Summary
 

Trenching

  • Sewer connection inspected and passed, and backfilled
  • Sewer to garage and South West corner of house completed
  • Connection to San Jose Water meter completed; inspection by the City of Monte Sereno on Monday afternoon (08/02/10)
  • Trench from underground cistern to storm sewer connection completed to sidewalk on Winchester
  • Trench to fill/overflow stubs for underground cistern completed 

Roof

  • All four (4) skylight curbs completed
  • Upper flat roof fascia completed
  • Two (2) of five (5) gable fascia ends completed
  • Twenty (20) linear feet of one hundred (100) linear feet of gable to flat roof connections completed
Our PERT chart, showing the remaining items to be completed before we can install the tapered foam roof crickets.

Our PERT chart, showing the remaining items to be completed before we can install the tapered foam roof crickets.

The trench from San Jose Water Company meter to the house was completed, with the 1-1/4 inch pipe installed.  The City of Monte Sereno will inspect this connection on Monday afternoon so we can backfill this trench.

The trench from San Jose Water Company meter to the house was completed, with the white 1-1/4 inch pipe installed. The City of Monte Sereno will inspect this connection on Monday afternoon so we can backfill this trench.

This congested trench area shows the water supply line (white 1-1/4 inch pipe) coming from the San Jose Water meter, and how it will be at least three (3) feet from PG&E's natural gas and electric services.

This congested trench area shows the water supply line (white 1-1/4 inch pipe) coming from the San Jose Water meter, and how it will be at least three (3) feet from PG&E

View of North East section of pool, showing completed trench to pool equipment (view unobstructed without the Hollywood Juniper).

View of North East section of pool, showing completed trench to pool equipment (view unobstructed without the Hollywood Juniper).

North end of South gable, which has been filled in with plywood.  Note the electrical conduit for the solar panels needs to be installed at the left side of the lower flat roof.

North end of South gable, which has been filled in with plywood. Note the electrical conduit for the solar panels needs to be installed at the left side of the lower flat roof.

Fully insulated (and enlarged) skylight curb completed on lower flat roof.

Fully insulated (and enlarged) skylight curb completed on lower flat roof.

There are three design details for the fascia:  the Upper Flat Roof fascia; Gable Roof fascia; and Lower Flat Roof fascia.

There are three design details for the fascia: the Upper Flat Roof fascia; Gable Roof fascia; and Lower Flat Roof fascia.

The Upper Flat Roof fascia has two (2) 2x8s with a one-inch space between them.  The fascia must extend above and below the SIP roof.  This fascia will be covered with natural zinc.

The Upper Flat Roof fascia has two (2) 2x8s with a one-inch space between them. The fascia must extend above and below the SIP roof. This fascia will be covered with natural zinc.

Upper Flat Roof fascia completed, showing the one-inch gap between the 2x6s.

Upper Flat Roof fascia completed, showing the one-inch gap between the 2x6s.

Under side of Upper Flat Roof, showing the detail where the remilled redwood will be.  Note the 2x6 will be covered with natural zinc.

Under side of Upper Flat Roof, showing the detail where the remilled redwood will be. Note the 2x6 will be covered with natural zinc.

The fascia for the Gable Roof consists of two (2) 2x8s.  There will be an air gap in the Gable Roof for a radiant heat barrier.

The fascia for the Gable Roof consists of two (2) 2x8s. There will be an air gap in the Gable Roof for a radiant heat barrier.

Fascia completed on West side of North Gable.

Fascia completed on West side of North Gable.

Detial on Gable Roof fascia (South West side of East gable).

Detail on Gable Roof fascia (South West side of East gable).

Green Home Building

Mid Century Style
Powered By Ringsurf