This project started in April 2008 and there have been a number of key milestones during the construction.

We reached the following key milestones during our construction:

  • Received approval from Site and Architecture Commission on 07/14/08
  • Started deconstructing parts of our original Eichler home on 09/30/08
  • Shipped our Redwood Decking and Douglas Fir beams to Jackel Enterprises on 10/09/08 for remilling
  • Drilled concrete piers on 11/06/09
  • Completed reshaping our swimming pool on 11/29/08
  • Received building permit on 12/05/08
  • Started excavation on 12/08/08
  • Completed drainage below foundation on 01/07/09
  • Completed insulating foundation on 01/27/09
  • Poured the 3 inch protection slab on 02/02/09
  • Poured the 14 inch structural slab on 03/11/09
  • Shotcreted foundation walls on 04/08/09
  • Shotcreted garage walls on 04/30/09
  • Placed steel beams for main floor structure on 05/08/09
  • Placed 48 hollow core concrete panels for main floor on 05/12/09
  • Completed backfilling excavation around perimeter on 05/26/09
  • Framed bearing walls under our structural steel beams on 06/26/09
  • Installed interior stairs and bridges on 09/21/09
  • Welded posts to steel beams on 10/10/09