Posts Tagged ‘Ashford Formula’

Scott and Sue Review Progress

Sunday, October 11th, 2009

Scott Andersen and Sue Therrien are in California for a couple days and carved out some time to review our progress.  Scott has been involved in this project since the start and led the conceptual design.

Reviewing Progress

Scott liked the progress and thoroughly enjoyed testing the bridge.  We walked the around the site for over an hour, so Scott could get a good feel for the space.

Sue needed to do some shopping in Old Town, so Scott and Bryan slipped over to Whole Foods in Cupertino to take a look at the finished concrete floors there. 

Back to Los Gatos and to the Rose Collection.  We engaged Cherie Rose to put our color palette together so we thought Cherie should meet Scott.  Fortunately, Cherie was in her store on North Santa Cruz and Bryan was able to introduce Cherie to Scott and Sue.

We went back to 1621 Rebel Way where Jo-Anne made dinner.  Bryan and Scott agreed to meet tomorrow morning at Hotel Los Gatos for a design session.

Sue and Scott arrive, right on schedule.

Sue and Scott arrive, right on schedule, to review our progress.

Scott testing the bridge.  He approved.

Scott testing the bridge. He approved.

Scott reviewing the stained and polished floor in Whole Foods, in Cupertino.

Scott reviewing the stained and polished floor in Whole Foods, in Cupertino.

 

More polished concrete in Whole Foods.  This section is just 'in the cream' of the concrete and not in the aggregate.  This is a nice finish.

More polished concrete in Whole Foods. This section is just 'in the cream' of the concrete and not in the aggregate. This is a nice looking finish.

Discussing Next Steps with Bill Brown

Friday, September 25th, 2009

We put our project on hold for three months while the stairs and two bridges were designed, engineered, fabricated and installed.

Bill Brown met Bryan at the project site today and reviewed the stairs and bridges.  And tested each of them.

Discussion with Bill Brown

Bryan met with Bill for several reasons.  First, Bill wanted to see the stairs and bridges, and then he wanted to know where we are with the project and what the next steps are.  Also, Bill wanted to ensure that we were satisfied with the billings to date and answer any questions that we had.

Bryan showed Bill the various components for the stairs and bridges, and explained that the 14 posts that will be welded to the steel I-beams should be delivered next week.  Larson Steel will do the field welding and ensure the posts are solidly in place before we can pour the next (final) layer of concrete.

Bill would prefer to do one monolithic pour for the entire 5-1/4 inches of concrete on the main floor.  Also, we require 3 more inches of concrete in the lower level.  Bill recommended that we work quickly on our ‘colors’ and decide on how much tint we require in the concrete mix.  Bryan mentioned that John Minton recommended that we do a monolithic pour so we take out as much of the camber in the hollow core concrete panels.

In reviewing the elevation for the finished floor, Bill pointed out that we have now established that level with the brackets in the Bridge Hall that support the GlassWalk floor system.  Bryan noted that Larson Steel will need to remove part of the bracket at each end of the bridge so there is sufficient depth for the concrete.

Our next steps include the following:

  • Receive the posts and weld the posts into place.
  • Bill’s team will ensure the current forms are in the correct position and put in the remaining forms with reinforcing steel and/or wire mesh.
  • We will have the radiant heating and cooling PEX installed, with supply/return lines to the various manifolds.
  • Pour the main floor.
  • Pour the lower level.
  • Strip the forms.
  • After 28 days (or so), grind and polish the concrete as required.

Bill will be working on designing the concrete mix so it will include the appropriate amount of slag that works with the sealant (Ashford Formula or equivalent), the desired aggregate size (depending on how much grinding we want in the surface), the hardness of the concrete (PSI), and the amount of water required. 

He will design a mix that considers the various objectives and will limit the risk and degree of cracking that will occur (remember, concrete cracks).

Bill Walks the Property

Being very skilled around project sites and walking across steel beams, Bill tested the bridge by walking across it and bouncing in the center.  Getting defensive, Bryan explained that there will be two layers of 3/4 inch plywood on the bridge with another 3/4 inch of hardwood flooring.  Bill smiled said that he will test the bridge when it is completed.

Regarding the exposed edges of concrete and steel I-beams, Bill recommended that we grind the exposed face of the concrete and not use any stainless steel trim.

Bill Brown testing the bridge.  It passed his preliminary inspection and Bill will provide his opinion on completion.

Bill Brown testing the bridge. It passed his preliminary inspection and Bill will provide his opinion on completion.

Bill checking the vertical gap between the steel I-beam and the stair stringer to ensure the 1x2 stainless steel post will fit.  He believes it will, just.

Bill checking the vertical gap between the steel I-beam and the stair stringer to ensure the 1x2 stainless steel post will fit. He believes it will, just.

Green Home Building

Mid Century Style
Powered By Ringsurf