Dave Merchant milled three of our 6×10 beams at his Out of the Woods operation in Bonny Doon today. That was after Darrel Kelly (Builder’s Energy Services Inc.) stopped by the project site to see our insulation being installed around our slab. At the end of the day, Pete Janovich (Bill Brown Construction) coordinated with Dave Edwards (Earth Bound Homes) on how, now that the existing East and West exterior walls of the original house are secured to the foundation, the two temporary steel beams can be removed.
We’re moving forward.
Darrel Kelly Verifies Our Slab Insulation
Under the LEED-H program, the Green Rater assigned to our application is Darrel Kelly. A Green Rater has the following responsibilities within the LEED for Homes Program:
- Oversight of all verification services on a LEED for Homes registered project
- Communication link between Provider Organization and Project Team
- Verification that Project Submittal Package is complete and delivery to Provider QAD
Bryan called Darrel this morning and mentioned that it would be good for him to visit the project site as the insulation is being secured around the perimeter of the slab and could be verified today. Darrel said he would be right over.
Darrel took the opportunity to walk around the site, noting various changes since his last site visit in January 2010.

The entire perimeter of the house is insulated with at least one layer of rigid foam (R-10). Here, on the south side of the house, there are two layers of rigid foam. This location is in the garage, just over the Wine Cellar. The sewage ejector is just to the left in this photo.

Darrel Kelly arrived and started taking photos. He verified the insulation that now covers the foundation slab.

As Darrel reviewed the project site, he took a number of photos, including a photo of our FSC lumber.

More photo verification of the FSC-certified 2x4s studs.

Carlos trims the custom flashing to fit over the foam, which is insulating the edge of the slab above grade.
Milling Three Reclaimed Douglas Fir Beams to Size in Bonny Doon
After Darrel left, Bryan went to Bonny Doon (again) and worked with Dave Merchant as he milled three 6×10 reclaimed Douglas Fir beams. Dave has a Wood Mizer LT70 mill, with remote control, that he runs in his Out of the Woods operation.
Bryan had spent some time yesterday reviewing the reclaimed 6×12 Douglas Fir beams that we had purchased so he was working with Dave to ensure our requirements were met for these three beams.

Dave brings the three beams over to the milling location while his helper, Ben, directs him.

Dave, operating the Wood Mizer saw, prepares to mill the 6x12 beam to 9-9/16 inch tall.

Dave measures the beam to ensure it was milled as required. The other two milled beams on on the left.

Going down Empire Grade into Felton. The road goes through a second-growth Redwood forest.

Bryan stopped for a few minutes to enjoy the quiet sanctity of the second growth Redwood forest on Empire Grade.
Coordinating the Removal of the Two Temporary Steel Beams
We preserved the East and West walls of the existing house. We did so by using 60 ft long steel beams, mounted on concrete piers. The walls were attached to the steel beams, and secured in place at the top and bottom. This temporary structure was designed and engineered to withstand 100 mph winds.
With the foundation completed and the insulation in place (covered by the custom zinc-plated steel flashing), we could secure the mudsill to the concrete and square up each wall. We need to coordinate the removal of the temporary steel beams with Pete Janovich, who put them in.
Pete arrived at the job site and reviewed each of the concrete piers supporting the temporary steel beams. Pete will have his team unbolt the temporary steel beams and move them sufficiently for Dave’s team to complete the framing.
We will have a crane on site next week to unload the long beams, including the 40 ft 6×12 wooden beam. At that time, we will use the crane to remove the two temporary steel beams and load them on a truck.

Pete Janovich (left) and Dave Edwards (right). Note the temporary steel beam supporting the existing East wall behind them.

Pete and Dave review each temporary steel beam so Dave's team can complete the framing and continue working expeditiously.

The first SIP wall panel goes into place on the South wall facing Via Sereno. The remainder of the wall will be in place within a week.