Posts Tagged ‘sewage ejector reservoir’

Connecting the Sanitary Sewer Lines

Thursday, April 2nd, 2009

Sewage flows down hill.

Connecting the Sewer Lines

We have three sewer lines that need to exit the house.  One line is from the west side of the main floor, another from the kitchen area, and the third from the sewage ejector in the lower level.  All three sewer lines must flow with gravity to the sewer line at the street (Via Sereno).

To flow, the sewer lines must be higher than the connection at the street.  Sewage does not flow up hill.

The sewage ejector pushes the sewage up, so it can exit the house at whatever elevation is required and then simply flow down hill to the street.  The sewer line from the kitchen is small, and can exit the house at the kitchen and then flow to the connection to the street, or it can exit at the side of the house and flow to that connection.

The tricky one is the sewer line exiting the west side of the house as it must be high enough to have sufficient drop to the connection at the street while, at the same time, being low enough to pick up waste from the three bathrooms and the laundry room on the main floor.  If it is too low then … it simply won’t work.

Complication

We didn’t know where the sewer line was capped from the street.  Locating the sewer line took more than two hours and multiple phone calls.  It was buried in the dirt behind the south window well.  Once we found it, Bryan spray painted it red.

Capped sewer line to street, spray painted red.

Capped sewer line to street, spray painted red.

Inspecting the Reinforcing Steel and Establishing Window Requirements

Thursday, February 26th, 2009

Our plan is to pour the foundation slab on Monday, March 2.  This requires having the City of Monte Sereno inspect and approve the progress to date.  Bryan called the City of Monte Sereno to request an inspection for Friday, February 27 and learned that no inspections will be done on that date.  OK, we just slipped by a day and the inspection will be between 10:00 am and noon on Monday, March 2.

Jessica from Duquette Engineering arrived to review the structural steel.  Since she had not been to the project site before, Thien had her look at this construction blog to prepare for her site visit (that rocks!). 

Jessica inspects the reinforcing steel (dimensions, spacing and overlaps).

Jessica inspects the reinforcing steel (dimensions, spacing and overlaps).

(more…)

Green Home Building

Mid Century Style
Powered By Ringsurf